project info
Start date: 16 November 2015
End date: 20 February 2019
funding
Fund: Cohesion Fund (CF)
Total budget: 12 413 796,36 €
EU contribution: 10 551 726,91 € (85%)
programme
Programming period: 2014-2020
Managing authority: Ministerstvo dopravy - Odbor fondů EU

Increase in traction power TNS, TNS Saint and SPS Bílina – Phase II

The object of the project is the reconstruction of the technology of the substation Světec, its technological and construction parts and subsequent distributions of high voltage (vn) and low voltage (nn), including connection to the traction line. The reconstruction will be carried out in the form of construction of a new operating building in a prefabricated design. As part of the project, a switching station of 3 kV DC will be set up in the railway station. Bílina for the purpose of improving operating conditions of the power supply of the traction line and increasing line throughput.

Flag of Czechia  Prague, Czechia