Start date: 10 July 2017
End date: 31 October 2019
funding
Fund: Cohesion Fund (CF)
Total budget: 57 827 668,00 €
EU contribution: 49 153 520,00 € (85%)
programme
Programming period: 2014-2020
Managing authority: Ministerstvo dopravy - Odbor fondů EU

Line speed increase in the section Řikonín – Vlkov u Tišnova

The construction is located on the two-track national line No.250 Brno – Havlíčkův Brod in the section Řikonín – Vlkov u Tišnova. The line is electrified by alternating traction of 25 kV, the current line speed is 100 km/h. Níhov stop is located in the solved line section, which will also be the subject of reconstruction.Content of the construction is reconstruction of the railway substructure, superstructure, bridges, tunnels and technological equipment with the aim of increasing line speed and safety of railway operation.

Flag of Czechia  Prague, Czechia