Kohesio: discover EU projects in your region

project info
Start date: 15 July 2020
End date: n/a
funding
Fund: Cohesion Fund (CF)
Total budget: 73 604 340,00 €
EU contribution: 62 563 684,00 € (85%)
programme
Programming period: 2014-2020
Managing authority: Ministerstvo dopravy - Odbor fondů EU
intervention field
European Commission Topic
European Commission Topic

Change of traction system to AC 25 kV, 50 Hz in the section Nedakonice — Říkovice

The building is located on the two-track national line No. 330 (according to KJŘ), respectively no. 305F and 316A (according to TTP) Přerov — Břeclav. The line is electrified in the Přerov — Nedakonice section with a direct current traction system of 3 kV, in the Nedakonice — Břeclav section with an alternating traction system of 25 kV, 50 Hz. Line speed is 160 km/h, brake distance 1 000 m. The project solves the transition to a uniform 25 kV, 50 Hz AC power supply system and ensures compliance with the connection conditions of the distribution system.

Flag of Czechia  Prague, Czechia