project info
Start date: 11 February 2016
End date: 30 December 2019
funding
Fund: Cohesion Fund (CF)
Total budget: 410 585,66 €
EU contribution: 349 057,60 € (85,64%)
programme
Programming period: 2014-2020
Managing authority: Estrutura com a natureza jurídica de estrutura de missão, criada pelo Decreto-Lei n.º 137/ 2014 de 12 de setembro
intervention field
European Commission Topic

SAR SANTA CRUZ

In addition to the increase in the extension of the service to populations not yet served in the area of influence of the System, the investment will allow the closure of the System and the optimisation of the operation and profitability of the respective investment related to the existing sewage treatment plant. This low network is dimensioned and will serve about 236 inhabitants of the parish of Santa Cruz, which implies a coverage rate will increase from 36 % to 44 % in the area of the System.

Flag of Portugal  Alto Minho Subregion, Portugal