project info
Start date: 1 April 2018
End date: 8 January 2019
funding
Fund: European Regional Development Fund (ERDF)
Total budget: 3 460 716,98 €
EU contribution: 1 038 215,09 € (30%)
programme
Programming period: 2014-2021
Managing authority: Ministerstvo průmyslu a obchodu / Útvar náměstka ministra pro fondy EU

Reducing the energy performance of building No.91

The project deals with the reconstruction and revitalisation of production premises (halls No. 91) in the area of OZ Elektromotory Mohelnice, which does not meet the required standards and standards for the newly planned production and installation of engines with gearbox (drives). In particular, new insulation of the roof, perimeter walls and sheaths of the reconstructed part of the building is planned, and a new method of heating is also planned. An integral part of the project is also new hot water heating using renewables and LED lighting. a.

Flag of Czechia  Prague, Czechia